Remodeling your home is a big decision and can become quite an undertaking.
There are many details to be considered, selections to choose, and coordinating the schedules of all those involved. It also can disrupt your home and the routines you have in place, particularly when you are remodeling a kitchen which is the center and the hub of the home.
With the current cost of a kitchen remodel falling between $22,000 and $58,000, families with little savings and smaller budgets are often left little choice but DIY and Big Box store remodeling, leaving room for costly mistakes and cheap, low quality products being installed.
We have found a way to give you and your family a new kitchen with limited disruption to your home as well as your savings account with the 10 day $10,000 kitchen remodel. It also gives you the opportunity to sit back and watch as professionals with many years of experience do the job in a clean and efficient manner.
Read more below to see an example of this 10 day $10,000 kitchen remodel.
How it works
Steven Schmidt Construction (SSC) has planned an efficient remodeling schedule that limits the construction disruption of the home to 10 days with affordable material selections included in the $10,000 overall project budget.
The first step is meeting with the client and determining needs and wants, as well as performing an initial measure. We then determine a new floor plan and discuss material finishes and selections with the customer.
Upon approval of the new floor plan and materials, we perform a final measure and place orders for all the selections involved.
In order to meet the 10 day time commitment, the customer must have selections approved 3 weeks prior to construction start date (for ordering purposes and timely delivery).
Budget includes:
Cabinets: Design, measure & install Wellborn Select Series, Franklin oak
Laminate tops: post form standard laminate
Flooring: floating laminate floor or sheet vinyl overlay of existing, 90 SF
Labor: demo and reinstall cabinets, misc repairs
Drywall repairs
Plumbing: R&R, new SS sink w/ chrome delta 400 faucet
Electrical: update all outlets, add 2 more outlets, install 2 fixtures
2- light fixtures
Paint walls & ceiling
Total
$ 9975.00
Timeline:
Day 1: remove plumbing, tops, cabinets
Day 2: add and update electrical
Day3 –day 4: drywall repair
Day 5: install cabinets, misc trim & measure tops
Day 6: prep & paint
Day 7: paint
Day 8: install tops, plumbing & electrical
Day 9: install flooring
Day 10: install appliances, touch ups
Notes
*Owner share of work associated with the project:
do all final cleaning
furnish all appliances
select all finishes prior to ordering cabinets
all existing millwork will be reused
any floor repairs needed due to rotten subfloor not included
all appliances will be installed in existing locations
Possible upgrade options:
*Costs are approximate only
| Full Overlay cabinet fronts (Prairie Oak) | + $900 |
| Premier Series Upgrade (Dovetail Maple Drawer with Cushion Close, + more options) | + $800 |
| Matching door panels at cabinet ends | + $350 |
| Cambria or Granite countertop | + $2,500 |
| Under-cabinet lighting | + $600 |
| Appliance package with dishwasher | + $1800 |